Siba

Overview

Field and Infrastructure Layout

Source: Company filing, GCA report.

(1) Contract expiry in 2032. (2) New/amended contract would be required; this would be at the discretion of the Iraq government. (3) Farm-out completion subject to pre-emption rights and government

approvals.

(4) Oil exploration not included in the current licence; separate licence would need to be agreed with the government.

Gas field at development stage with a 20-year service

contract

(1)

and an optional 5 year extension period

Current shortage of gas for power generation in

southern Iraq expected to provide a ready market

for gas

Condensate production remunerated under the same

terms as the contracted gas offtake

Further upside to reserves and scope to increase the gas

offtake quantity

(2)

Farm-out of 15% revenue WI/20% cost WI to EGPC

announced in October 2016

(3)

Potential for future oil exploration

(4)

Field Development Update

Overall project progress around 87%

First gas and full contracted production targeted for 2017

and 2018, respectively

Three wells drilled and ready to produce; supply pipelines

completed

Zubair

Al Fao

Depot

Khour Al Zubair

Depot

Dry gas pipeline

LPG pipeline

Condensate pipeline

Existing Condensate pipeline

Transfer Points

Process Facilities

Contracted gas offtake of 100 mmscf/d

17